CAPM Practice: Explain the components of an adaptive plan
Question 44 of 60 in Explain the components of an adaptive plan
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Budget is fixed and scope is variable — lowest priority backlog items are cut if budget runs low
Explanation
In adaptive projects with fixed budgets, scope is the variable. The team delivers the highest-priority items first; if budget is exhausted before all items are complete, lower-priority items are cut — ensuring the most valuable work is always done first.
Key Concept
This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).