CAPM Practice: Explain the components of an adaptive plan
Question 45 of 60 in Explain the components of an adaptive plan
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Detailed planning is deferred until it is needed, rather than planning everything upfront
Explanation
Just-in-time planning means detailed decisions are made when needed, not months in advance. This reduces waste (plans that must be revised) and improves decision quality by using the most current information available.
**Why not A:** Just-in-time refers to when detailed planning happens, not to rescheduling cancelled meetings.
**Why not C:** Planning at the deadline with no buffer is too late; just-in-time means planning when the information is needed, not after it is needed.
**Why not D:** Just-in-time concerns the timing of planning decisions relative to need, not working hours.
Key Concept
This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).