CAPM Practice: Explain the components of an adaptive plan
Question 37 of 60 in Explain the components of an adaptive plan
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: A two-dimensional visualization of user stories organized by user journey (horizontal) and priority (vertical), revealing MVP slices
Explanation
User story mapping organizes stories along the user's journey horizontally (activities and tasks) with priority/detail shown vertically. This reveals natural release slices and helps plan iterations that deliver end-to-end user value.
**Why not A:** A dependency network is a separate planning tool — often called a dependency map or precedence diagram — that shows technical ordering constraints. A Story Map organizes stories by user journey and priority, not by inter-story dependencies.
**Why not C:** User stories are backlog items tied to user needs and desired outcomes; their geographic origin is irrelevant to planning. This choice misapplies the word "map" in a literal geographic sense rather than in its planning context.
**Why not D:** A code flow or branching strategy diagram is a DevOps or engineering artifact concerned with version control. A Story Map is a product planning tool focused on user activities and release slicing, not source control workflows.
Key Concept
This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).