CAPM Practice: Explain the components of an adaptive plan
Question 38 of 60 in Explain the components of an adaptive plan
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Infrastructure work is included in early iterations as 'enabling stories' or 'architectural runways' that unblock feature development
Explanation
Enabling stories or architectural runway backlog items capture foundation work that enables future features. Including them in early iterations ensures the team has the technical foundation needed without a separate pre-project waterfall phase.
**Why not A:** Ignoring architectural work leaves features blocked.
**Why not C:** A separate waterfall phase contradicts adaptive planning.
**Why not D:** Full upfront design is not required; architecture evolves iteratively.
Key Concept
This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).