Skip to content
CAPMHard

CAPM Practice: Explain the components of an adaptive plan

Question 38 of 60 in Explain the components of an adaptive plan

Pick an answer below — you'll get the explanation instantly, no signup.

How do adaptive plans handle architectural and infrastructure work that must be completed before feature development can begin?
Show answer & explanation

Correct answer: Infrastructure work is included in early iterations as 'enabling stories' or 'architectural runways' that unblock feature development

Explanation

Enabling stories or architectural runway backlog items capture foundation work that enables future features. Including them in early iterations ensures the team has the technical foundation needed without a separate pre-project waterfall phase.

Key Concept

This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free