An adaptive team's 'definition of done' (DoD) is BEST established:
Show answer & explanation

Correct answer: By the team collectively to reflect their quality standards for completing work

Explanation

The Definition of Done is established by the development team (ideally with input from the product owner and organizational standards). It reflects the team's quality standards — what conditions must be true for work to be considered complete. Team ownership of the DoD ensures commitment and shared accountability for quality, rather than externally imposed criteria.

**Why not A:** A PMO template may provide organizational quality standards that the DoD should respect, but imposing a standard template removes team ownership. The DoD must reflect the specific team's work and quality practices, and an externally imposed checklist undermines the commitment and shared accountability that make it effective.

**Why not B:** The product owner defines what to build and sets acceptance criteria for individual backlog items, but the DoD is a team-wide quality standard that applies to all work. Having the product owner dictate the DoD confuses business requirements with the team's own standards for completing work.

**Why not D:** The Scrum Master coaches the team and may facilitate the conversation about the DoD, but does not set it. Industry best practices can inform the discussion, but a DoD handed down by the Scrum Master would not reflect the team's collective commitment to its own quality standards.

Key Concept

This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).