CAPM Practice: Explain the components of an adaptive plan
Question 4 of 60 in Explain the components of an adaptive plan
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Plans at a higher level across multiple sprints to identify when groups of features will be ready for release
Explanation
Release planning spans multiple sprints and addresses when groups of features will be ready for a product release. It uses velocity and backlog estimates to forecast release dates or define what can be included in a release by a specific date. Sprint planning is more detailed, focused on a single sprint's goal and backlog selection. Release planning operates at a higher, less granular level.
**Why not A:** Deciding which team members will work on which stories is not what distinguishes release planning. Release planning works at the feature level across multiple sprints, and in adaptive teams members self-organize and select work rather than being assigned stories during release planning.
**Why not B:** Release planning is a collaborative activity. The product owner prioritizes the backlog, but the team provides the estimates and velocity data needed to forecast what can be released and when.
**Why not C:** Release plans are not fixed at project start. They are revisited and updated as velocity data, stakeholder feedback, and priorities change throughout the project.
Key Concept
This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).