CAPM Practice: Explain the components of an adaptive plan
Question 59 of 60 in Explain the components of an adaptive plan
Show answer & explanation
Correct answer: An assessment of available team hours (excluding vacations, meetings, training) used to calibrate realistic iteration commitments and avoid over-loading the team
Explanation
Team capacity planning calculates available hours per iteration by subtracting known unavailability (meetings, PTO, training). When combined with velocity data, it enables realistic iteration commitments — preventing the over-commitment that leads to incomplete sprints.
Key Concept
This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free