CAPM Practice: Explain the components of an adaptive plan
Question 59 of 60 in Explain the components of an adaptive plan
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: An assessment of available team hours (excluding vacations, meetings, training) used to calibrate realistic iteration commitments and avoid over-loading the team
Explanation
Team capacity planning calculates available hours per iteration by subtracting known unavailability (meetings, PTO, training). When combined with velocity data, it enables realistic iteration commitments — preventing the over-commitment that leads to incomplete sprints.
**Why not A:** A capacity plan is not a skills development plan. Identifying the technical skills team members need to build belongs to team development and training activities; a capacity plan measures how many hours the team actually has available in an iteration.
**Why not B:** A capacity plan does not set a cap on team size. Agile guidance favors small teams, but capacity planning assesses the real availability of the existing team so iteration commitments stay realistic.
**Why not C:** A capacity plan is not a staffing growth plan. It looks at the team's actual availability for upcoming iterations, not at adding members over the project duration.
Key Concept
This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).