CAPM Practice: Explain the components of an adaptive plan
Question 60 of 60 in Explain the components of an adaptive plan
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Technical enablers are included in the backlog as 'enabling stories' or 'architectural runway' — planned alongside feature work to ensure the team has the technical foundation needed for upcoming features
Explanation
Enabling stories fund technical foundation work that unblocks future feature delivery. Including them alongside feature stories in the backlog and iterations ensures the architectural runway keeps pace with feature demand — preventing technical debt from blocking future delivery.
Key Concept
This question covers Explain the components of an adaptive plan under Explain the components of an adaptive plan (Agile Frameworks/Methodologies).