CAPM Practice: Determine how to prepare and execute task management steps
Question 35 of 60 in Determine how to prepare and execute task management steps
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Work that meets all criteria in the Definition of Done, including testing, review, and documentation — truly complete
Explanation
'Done done' emphasizes that work is fully complete — meeting all Definition of Done criteria (coded, tested, reviewed, documented, accepted) — not just 'development complete' or 'mostly done.' It prevents hidden work from accumulating.
**Why not A:** Deployment to production and customer acceptance may or may not be part of a team's Definition of Done. 'Done done' refers to meeting all of the agreed Definition of Done criteria, not specifically to production release or customer acceptance.
**Why not B:** 'Done done' does not mean performing work twice. The repetition emphasizes that work is truly complete against the Definition of Done, not that it has been redone for quality assurance.
**Why not C:** 'Done done' has nothing to do with when in the iteration work is completed. It describes the completeness of the work against the Definition of Done, regardless of timing.
Key Concept
This question covers Determine how to prepare and execute task management steps under Determine how to prepare and execute task management steps (Agile Frameworks/Methodologies).