CAPM Practice: Determine how to prepare and execute task management steps

Question 36 of 60 in Determine how to prepare and execute task management steps

A team uses a digital Kanban board. WIP limits show that the testing column is always at its limit while development items queue up. What should the team do?
Show answer & explanation

Correct answer: Identify the testing bottleneck root cause and add capacity or reduce testing WIP limit to create pressure to resolve the constraint

Explanation

A consistently full testing column is a bottleneck (constraint). The Theory of Constraints says to identify and address the constraint — whether by adding testers, automating tests, or cross-training developers to test — rather than hiding it by raising WIP limits.

Key Concept

This question covers Determine how to prepare and execute task management steps under Determine how to prepare and execute task management steps (Agile Frameworks/Methodologies).