CAPM Practice: Determine how to prepare and execute task management steps
Question 36 of 60 in Determine how to prepare and execute task management steps
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Identify the testing bottleneck root cause and add capacity or reduce testing WIP limit to create pressure to resolve the constraint
Explanation
A consistently full testing column is a bottleneck (constraint). The Theory of Constraints says to identify and address the constraint — whether by adding testers, automating tests, or cross-training developers to test — rather than hiding it by raising WIP limits.
**Why not A:** Raising the testing WIP limit hides the constraint rather than resolving it. More items would sit in testing at once, increasing cycle time without increasing the team's actual testing throughput.
**Why not C:** Testing earlier can be a helpful practice, but doing so without addressing the bottleneck leaves the underlying constraint in place, so development items will continue to queue up.
**Why not D:** Removing WIP limits eliminates the very signal that exposed the bottleneck. Work would accumulate unchecked in testing and flow would get worse, not better.
Key Concept
This question covers Determine how to prepare and execute task management steps under Determine how to prepare and execute task management steps (Agile Frameworks/Methodologies).