Skip to content
CAPMMedium

CAPM Practice: Determine how to prepare and execute task management steps

Question 27 of 60 in Determine how to prepare and execute task management steps

Pick an answer below — you'll get the explanation instantly, no signup.

How does a team handle a task that is larger than expected and cannot be completed within the iteration?
Show answer & explanation

Correct answer: Split the task, complete what can be done, and return the remainder to the backlog for the next iteration

Explanation

When tasks exceed iteration capacity, the team splits them — completing the deliverable portion and returning incomplete work to the backlog. The iteration still ends on schedule. Only fully 'done' work is counted toward velocity.

Key Concept

This question covers Determine how to prepare and execute task management steps under Determine how to prepare and execute task management steps (Agile Frameworks/Methodologies).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free