CAPM Practice: Determine how to prepare and execute task management steps
Question 27 of 60 in Determine how to prepare and execute task management steps
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Split the task, complete what can be done, and return the remainder to the backlog for the next iteration
Explanation
When tasks exceed iteration capacity, the team splits them — completing the deliverable portion and returning incomplete work to the backlog. The iteration still ends on schedule. Only fully 'done' work is counted toward velocity.
Key Concept
This question covers Determine how to prepare and execute task management steps under Determine how to prepare and execute task management steps (Agile Frameworks/Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free