CAPM Practice: Determine how to prepare and execute task management steps
Question 26 of 60 in Determine how to prepare and execute task management steps
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Frequently merging code changes into a shared repository with automated builds and tests to catch issues early
Explanation
CI is the practice of developers frequently integrating their work (at least daily) with automated builds and tests running on each integration. This catches integration issues immediately rather than at the end of an iteration.
**Why not A:** Integrating only at the end of each iteration delays finding problems, which is exactly what CI avoids.
**Why not C:** CI concerns merging code changes, not consolidating project plans.
**Why not D:** Onboarding team members is unrelated to continuous integration.
Key Concept
This question covers Determine how to prepare and execute task management steps under Determine how to prepare and execute task management steps (Agile Frameworks/Methodologies).