CAPM Practice: Determine how to prepare and execute task management steps
Question 30 of 60 in Determine how to prepare and execute task management steps
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Use timeboxed spikes to investigate and reduce uncertainty before committing to implementation tasks
Explanation
Technical uncertainty should be addressed through spikes — timeboxed investigations. The spike produces knowledge (not product features), enabling better estimation and planning for the actual implementation task in a future iteration.
**Why not A:** Estimating uncertain tasks like known ones produces unreliable estimates; uncertainty should be reduced first.
**Why not B:** Avoiding uncertain work only defers risk and may leave critical value undelivered.
**Why not D:** Working without visibility removes transparency and inspection, letting problems surface too late.
Key Concept
This question covers Determine how to prepare and execute task management steps under Determine how to prepare and execute task management steps (Agile Frameworks/Methodologies).