CAPM Practice: Determine how to plan project iterations

Question 58 of 61 in Determine how to plan project iterations

Pick an answer below — you'll get the explanation instantly, no signup.

What is the purpose of the daily standup (daily Scrum) in the context of iteration execution?
Show answer & explanation

Correct answer: To synchronize the team, share what was done, what will be done, and identify impediments

Explanation

The daily Scrum is a 15-minute inspection and adaptation event for the team. It creates transparency about progress toward the Sprint Goal and surfaces impediments for quick resolution — not a status report to management.

**Why not A:** Code quality metrics and defect counts are appropriate topics for sprint reviews, retrospectives, or continuous integration dashboards — not the daily standup. The standup is deliberately time-boxed at 15 minutes and focused on coordination and impediment identification, not quality trend analysis.

**Why not B:** The daily Scrum is explicitly a team synchronization event for the team itself, not a reporting mechanism for management. Using it for performance evaluation would destroy psychological safety, cause team members to be guarded rather than transparent about problems, and transform a collaborative coordination tool into top-down surveillance.

**Why not C:** The daily standup is not a re-planning session. Completely replanning the iteration every day would destroy the sprint commitment, prevent the team from developing a sustainable cadence, and undermine the stability of the sprint goal. Day-level tactical adjustments are expected, but the sprint scope and goal remain anchored for the sprint's duration.

Key Concept

This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).