CAPM Practice: Determine how to plan project iterations
Question 57 of 61 in Determine how to plan project iterations
Pick an answer below — you'll get the explanation instantly, no signup.
Why should iterations be kept at a consistent length throughout a project?
Show answer & explanation
Correct answer: Consistent cadence builds predictable rhythm, makes velocity reliable, and simplifies planning
Explanation
Consistent iteration length creates a predictable heartbeat for the team and stakeholders. It makes velocity measurements comparable across iterations and helps teams build a sustainable pace.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).