CAPM Practice: Determine how to plan project iterations

Question 52 of 61 in Determine how to plan project iterations

Pick an answer below — you'll get the explanation instantly, no signup.

How does capacity-based iteration planning differ from velocity-based planning?
Show answer & explanation

Correct answer: Capacity-based planning uses actual available hours per team member, while velocity-based planning uses historical throughput in story points

Explanation

Capacity-based planning calculates available work hours (accounting for holidays, meetings, etc.) and estimates task hours. Velocity-based planning uses historical story point throughput. Both can be used together for more accurate iteration planning.

Key Concept

This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).