CAPM Practice: Determine how to plan project iterations

Question 51 of 61 in Determine how to plan project iterations

Pick an answer below — you'll get the explanation instantly, no signup.

During iteration planning, the team realizes the Product Owner's top priority story has unclear acceptance criteria. What should happen?
Show answer & explanation

Correct answer: Clarify acceptance criteria with the Product Owner before committing to the story

Explanation

Stories with unclear acceptance criteria violate the Definition of Ready. The team should work with the Product Owner during planning (or ideally in prior refinement) to clarify criteria before committing.

**Why not B:** Skipping the top-priority story ignores the Product Owner's priorities when the criteria can simply be clarified.

**Why not C:** Committing without clear acceptance criteria leaves 'done' undefined and risks rework.

**Why not D:** The Product Owner owns acceptance criteria; writing them without consultation risks building the wrong thing.

Key Concept

This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).