CAPM Practice: Determine how to plan project iterations
Question 12 of 61 in Determine how to plan project iterations
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Use the average velocity (≈35) and acknowledge variability with a range of approximately 29-41 points
Explanation
Using the average (208/6 ≈ 35) with the observed range (29-41) gives the most honest and useful forecast. It acknowledges that velocity varies naturally and provides a realistic planning range. Using the maximum would consistently overcommit. Using only the most recent sprint (33) ignores the broader pattern. Presenting a range helps the product owner make realistic release planning decisions.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).