An adaptive team's velocity over six sprints was: 32, 38, 29, 41, 35, 33. The product owner wants to know how many story points they can expect in the next sprint. What is the BEST forecasting approach?
Show answer & explanation

Correct answer: Use the average velocity (≈35) and acknowledge variability with a range of approximately 29-41 points

Explanation

Using the average (208/6 ≈ 35) with the observed range (29-41) gives the most honest and useful forecast. It acknowledges that velocity varies naturally and provides a realistic planning range. Using the maximum would consistently overcommit. Using only the most recent sprint (33) ignores the broader pattern. Presenting a range helps the product owner make realistic release planning decisions.

Key Concept

This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free