CAPM Practice: Determine how to plan project iterations

Question 13 of 61 in Determine how to plan project iterations

Pick an answer below — you'll get the explanation instantly, no signup.

The sprint backlog belongs to:
Show answer & explanation

Correct answer: The development team, who owns and manages the sprint plan

Explanation

The sprint backlog belongs to the development team. The team selects sprint backlog items during sprint planning and manages how the work is accomplished during the sprint. The team can update, add tasks, or remove items as they learn more during the sprint — maintaining ownership of the HOW, while the PO owns the WHAT.

Key Concept

This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).