Skip to content
CAPMMedium

CAPM Practice: Determine how to plan project iterations

Question 54 of 61 in Determine how to plan project iterations

A new team is starting their first iteration. They have no historical velocity data. What is the best approach for their initial commitment?
Show answer & explanation

Correct answer: Make a conservative commitment, then adjust based on what they actually achieve

Explanation

Without historical data, new teams should start with a conservative commitment. After the first iteration, they'll have actual velocity data to inform future planning. This 'calibration sprint' approach is widely recommended.

Key Concept

This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free