CAPM Practice: Determine how to plan project iterations
Question 54 of 61 in Determine how to plan project iterations
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Make a conservative commitment, then adjust based on what they actually achieve
Explanation
Without historical data, new teams should start with a conservative commitment. After the first iteration, they'll have actual velocity data to inform future planning. This 'calibration sprint' approach is widely recommended.
**Why not A:** Skipping an iteration to collect data delays value delivery and does not actually produce velocity data. A team learns its velocity by doing real work in an iteration, not by observing.
**Why not C:** Committing to as many stories as possible sets the team up for overcommitment and likely failure, which damages stakeholder trust and team morale. Commitments should reflect realistic capacity, not a wish to impress.
**Why not D:** Velocity is specific to each team, its members, and how it estimates story points. Using another team's velocity directly is unreliable because their estimation scale and capacity differ.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).