CAPM Practice: Determine how to plan project iterations
Question 55 of 61 in Determine how to plan project iterations
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Identify dependencies between iterative and sequential components and build them into the iteration plan explicitly
Explanation
Hybrid projects require explicit coordination between iterative and sequential components. Iteration plans should identify touchpoints, dependencies, and handoffs between the two approaches to prevent bottlenecks and integration issues.
**Why not B:** Eliminating sequential components entirely ignores the legitimate reasons certain work must be done in a fixed order—regulatory approvals, hardware procurement, infrastructure builds, and other activities with hard dependencies cannot always be made iterative. Forcing all work into iterations can create artificial complexity and risk for work that is well-understood and benefits from a predictive approach.
**Why not C:** Keeping the two approaches completely separate defeats the purpose of hybrid project management. Agile and predictive components in the same project share resources, timelines, and deliverables; failing to integrate their planning creates gaps, missed handoffs, and schedule conflicts that can derail both tracks.
**Why not D:** Converting sequential work to agile sprints immediately is an overreaction that ignores the fundamental characteristics making certain work better suited to a predictive approach. Sequential work often exists because of regulatory, contractual, or technical constraints—wrapping it in sprint ceremonies does not make it inherently adaptive and can create process overhead without any corresponding benefit.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).