Skip to content
CAPMEasy

CAPM Practice: Determine how to plan project iterations

Question 60 of 61 in Determine how to plan project iterations

Pick an answer below — you'll get the explanation instantly, no signup.

What happens to incomplete user stories at the end of an iteration in Scrum?
Show answer & explanation

Correct answer: They return to the Product Backlog for re-prioritization

Explanation

In Scrum, incomplete stories are not considered 'done.' They return to the Product Backlog where the Product Owner re-prioritizes them. The Sprint ends at the timebox, regardless of completion.

**Why not B:** Nothing carries over automatically; the Product Owner decides when it is pulled again.

**Why not C:** Work that does not meet the Definition of Done cannot be marked complete.

**Why not D:** Sprints are fixed timeboxes and are not extended.

Key Concept

This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free