Skip to content
CAPMEasy

CAPM Practice: Determine how to plan project iterations

Question 60 of 61 in Determine how to plan project iterations

What happens to incomplete user stories at the end of an iteration in Scrum?
Show answer & explanation

Correct answer: They return to the Product Backlog for re-prioritization

Explanation

In Scrum, incomplete stories are not considered 'done.' They return to the Product Backlog where the Product Owner re-prioritizes them. The Sprint ends at the timebox, regardless of completion.

Key Concept

This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free