CAPMEasy
CAPM Practice: Determine how to plan project iterations
Question 60 of 61 in Determine how to plan project iterations
What happens to incomplete user stories at the end of an iteration in Scrum?
Show answer & explanation
Correct answer: They return to the Product Backlog for re-prioritization
Explanation
In Scrum, incomplete stories are not considered 'done.' They return to the Product Backlog where the Product Owner re-prioritizes them. The Sprint ends at the timebox, regardless of completion.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free