CAPM Practice: Determine how to plan project iterations
Question 60 of 61 in Determine how to plan project iterations
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: They return to the Product Backlog for re-prioritization
Explanation
In Scrum, incomplete stories are not considered 'done.' They return to the Product Backlog where the Product Owner re-prioritizes them. The Sprint ends at the timebox, regardless of completion.
**Why not B:** Nothing carries over automatically; the Product Owner decides when it is pulled again.
**Why not C:** Work that does not meet the Definition of Done cannot be marked complete.
**Why not D:** Sprints are fixed timeboxes and are not extended.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).