CAPM Practice: Determine how to plan project iterations
Question 61 of 61 in Determine how to plan project iterations
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: To track remaining work over time and forecast whether the iteration goal will be met
Explanation
A burndown chart shows remaining work (story points or hours) versus time. During execution, it helps the team see if they're on track. A chart flattening early may indicate blockers; rapid burning may mean under-commitment.
**Why not A:** A burndown chart tracks the team's collective remaining work, not which individual members completed their tasks. Using it to document individual completion shifts focus away from the team's shared progress toward the iteration goal.
**Why not B:** A burndown chart does not calculate return on investment. Value and ROI considerations inform backlog prioritization; the burndown chart only shows how much work remains over time.
**Why not C:** A burndown chart tracks remaining work in story points or hours, not planned daily spending. Budget and cost tracking are handled through other tools, not the iteration burndown.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).