CAPM Practice: Determine how to plan project iterations

Question 61 of 61 in Determine how to plan project iterations

Pick an answer below — you'll get the explanation instantly, no signup.

How does the team use a burndown chart during iteration planning and execution?
Show answer & explanation

Correct answer: To track remaining work over time and forecast whether the iteration goal will be met

Explanation

A burndown chart shows remaining work (story points or hours) versus time. During execution, it helps the team see if they're on track. A chart flattening early may indicate blockers; rapid burning may mean under-commitment.

Key Concept

This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).