CAPM Practice: Determine how to plan project iterations
Question 61 of 61 in Determine how to plan project iterations
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: To track remaining work over time and forecast whether the iteration goal will be met
Explanation
A burndown chart shows remaining work (story points or hours) versus time. During execution, it helps the team see if they're on track. A chart flattening early may indicate blockers; rapid burning may mean under-commitment.
Key Concept
This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).