Question 22 of 61 in Determine how to plan project iterations

Pick an answer below — you'll get the explanation instantly, no signup.

What is 'definition of ready' (DoR) in adaptive projects?
Show answer & explanation

Correct answer: A checklist of conditions a backlog item must meet before it can be selected for a sprint

Explanation

The Definition of Ready is a team-agreed checklist that items must meet to be eligible for sprint planning. Typical criteria: the story is understood (clear description), estimable (enough detail to size), small enough for one sprint, has defined acceptance criteria, and has no unresolved dependencies. DoR ensures sprint planning is efficient and items don't get stuck mid-sprint due to missing information.

**Why not A:** Whether the product is ready to release to end users is a release decision tied to the definition of done and release planning, not the definition of ready. DoR applies to individual backlog items before they enter a sprint.

**Why not B:** DoR has nothing to do with judging when a team member is productive. It describes the readiness of backlog items, not people.

**Why not C:** The Scrum Master does not approve who attends sprint planning, and DoR is not an attendance rule. It is a team-agreed checklist that backlog items must satisfy before they can be selected for a sprint.

Key Concept

This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).