Question 21 of 61 in Determine how to plan project iterations

Pick an answer below — you'll get the explanation instantly, no signup.

An adaptive team is planning a 6-sprint release. They want to ensure the most critical features are delivered first in case time runs out. What planning strategy supports this?
Show answer & explanation

Correct answer: Prioritize the product backlog by business value so the highest-value features are delivered in early sprints

Explanation

Value-first prioritization ensures that even if the project must end early (time runs out, budget exhausted, scope cut), the product contains its most valuable features. If a 6-sprint plan produces only 5 sprints of work, the product still delivers 5/6 of the planned value — rather than 0/1 (all-or-nothing at project end, which predictive completion models risk).

Key Concept

This question covers Determine how to plan project iterations under Determine how to plan project iterations (Agile Frameworks/Methodologies).