Skip to content
CAPMEasy

CAPM Practice: Determine how to gather requirements

Question 27 of 67 in Determine how to gather requirements

Pick an answer below — you'll get the explanation instantly, no signup.

What is meant by 'requirements sign-off' and why is it important?
Show answer & explanation

Correct answer: Formal stakeholder approval of requirements, establishing a baseline and shared commitment before development begins

Explanation

Requirements sign-off creates a formal baseline — stakeholders explicitly agree that requirements correctly represent their needs. This prevents rework from scope disputes later and establishes accountability for both parties: stakeholders approved requirements; the team will deliver them.

**Why not A:** The project manager signing the requirements document as author describes document authorship, not requirements sign-off. Sign-off is a stakeholder approval action where business stakeholders confirm that the documented requirements accurately represent their needs and agree to proceed on that basis.

**Why not B:** Requirements sign-off is not a legal signature required by regulatory bodies in most cases. While regulated industries may have specific approval requirements, requirements sign-off is fundamentally a project governance practice for establishing shared commitment and a requirements baseline.

**Why not C:** The BA signing off on their own work product describes self-review, not requirements sign-off. Sign-off involves stakeholders who provided the requirements confirming that the documented version is accurate and complete, establishing mutual accountability for what will be built.

Key Concept

This question covers Determine how to gather requirements under Determine how to gather requirements (Business Analysis Frameworks).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free