CAPM Practice: Determine how to gather requirements
Question 28 of 67 in Determine how to gather requirements
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: The approved set of requirements at a point in time, against which future changes are measured and managed
Explanation
A requirements baseline is the approved requirements at a specific point (typically after stakeholder sign-off). It enables change management — proposed changes are measured against the baseline to assess impact and maintain control of scope.
**Why not A:** Technical infrastructure and security requirements are a category of requirements content, not a definition of a baseline. A baseline is about governance and timing — the formal approval state of a requirements set — not about the subject matter of those requirements.
**Why not B:** A baseline has nothing to do with a minimum count of requirements. Establishing a baseline is a formal change-control action that freezes an approved version for comparison, regardless of how many requirements exist in it.
**Why not C:** An organizational template or standard set of requirements is sometimes called a "requirements library" or "standard requirements," not a baseline. A baseline is project-specific and time-stamped, capturing the exact approved state of requirements for that project at that moment.
Key Concept
This question covers Determine how to gather requirements under Determine how to gather requirements (Business Analysis Frameworks).