CAPM Practice: Determine how to gather requirements
Question 57 of 67 in Determine how to gather requirements
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: The level of detail at which requirements are specified — too high-level leaves implementation gaps; too granular constrains design unnecessarily. Right granularity matches what the team needs to proceed confidently
Explanation
Right-sized requirements enable action without over-constraining. User stories that are too large (epics) can't be committed to in one iteration. Requirements too fine-grained prescribe implementation and leave no room for developer creativity. BAs calibrate granularity to what the team needs.
**Why not A:** Requirement granularity is not about document length in pages. A lengthy document can still have poorly calibrated detail levels, with some requirements too vague and others excessively detailed. Granularity concerns the precision of individual requirements.
**Why not B:** The number of stakeholders who contributed to a requirement has no bearing on its granularity. Granularity refers to the level of specificity in how a requirement is expressed, not its authorship or collaboration breadth.
**Why not D:** Grammatical detail in a sentence is unrelated to requirement granularity. Granularity addresses how finely a functional or technical need is decomposed — whether it provides enough detail for the team without over-constraining the solution design.
Key Concept
This question covers Determine how to gather requirements under Determine how to gather requirements (Business Analysis Frameworks).