Skip to content
CAPMEasy

CAPM Practice: Determine how to follow and execute planned strategies or frameworks

Question 93 of 100 in Determine how to follow and execute planned strategies or frameworks

Pick an answer below — you'll get the explanation instantly, no signup.

What is the purpose of project initiation?
Show answer & explanation

Correct answer: To formally authorize the project and define its high-level scope, objectives, and initial requirements

Explanation

Project initiation is the phase where the project is formally authorized, typically through a project charter. This phase defines the project's high-level scope, objectives, and requirements, and identifies the project manager and their authority level.

**Why not A:** Closing out the project and documenting lessons learned describes the project closing phase, which occurs at the end of the project. Initiation is the beginning phase that authorizes the project, not the phase that concludes it.

**Why not B:** Executing deliverables and monitoring progress against the baseline describes the executing and monitoring/controlling phases. These occur after planning is complete, well beyond the initiation phase.

**Why not D:** Creating detailed work breakdown structures and activity sequences is part of the planning phase. Initiation establishes the high-level scope and authorization — detailed decomposition and sequencing happen during subsequent planning activities.

Key Concept

This question covers Determine how to follow and execute planned strategies or frameworks under Determine how to follow and execute planned strategies or frameworks (Project Management Fundamentals and Core Concepts).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free