CAPM Practice: Determine how to follow and execute planned strategies or frameworks
Question 93 of 100 in Determine how to follow and execute planned strategies or frameworks
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: To formally authorize the project and define its high-level scope, objectives, and initial requirements
Explanation
Project initiation (the Initiating Process Group) is where the project is formally authorized, typically through a project charter. Initiating defines the project's high-level scope, objectives, and requirements, and identifies the project manager and their authority level.
**Why not A:** Closing out the project and documenting lessons learned describes the Closing Process Group, which occurs at the end of the project. Initiation is the process group that authorizes the project at the beginning, not the one that concludes it.
**Why not B:** Executing deliverables and monitoring progress against the baseline describes the Executing and Monitoring and Controlling Process Groups. These rely on an approved baseline produced in planning, well beyond the initiation of the project.
**Why not D:** Creating detailed work breakdown structures and activity sequences is part of the Planning Process Group. Initiation establishes the high-level scope and authorization — detailed decomposition and sequencing happen during subsequent planning activities.
Key Concept
This question covers Determine how to follow and execute planned strategies or frameworks under Determine how to follow and execute planned strategies or frameworks (Project Management Fundamentals and Core Concepts).