CAPM Practice: Determine how to follow and execute planned strategies or frameworks

Question 12 of 100 in Determine how to follow and execute planned strategies or frameworks

Pick an answer below — you'll get the explanation instantly, no signup.

Chidi Khoury is working on a marketing campaign project at Gridstone AI. The communications management plan specifies weekly status reports to the sponsor every Friday. What is the most appropriate way for Chidi to follow this planned communication strategy?
Show answer & explanation

Correct answer: Send the weekly status report to the sponsor every Friday as specified in the plan

Explanation

Following the planned communication strategy means executing it as documented in the communications management plan. If weekly reports on Friday are specified, that is what should be done unless there is a reason to change the plan through proper change control.

**Why not A:** Waiting for the sponsor to request updates is a reactive approach that violates the communications management plan. The plan specifies proactive weekly reporting, and the project manager should follow the documented strategy.

**Why not B:** Sending daily updates instead of weekly reports deviates from the approved plan without proper change control. Increasing frequency without authorization changes the communication strategy and may overload the sponsor with unnecessary information.

**Why not C:** Combining weekly reports into monthly summaries reduces the communication frequency below what was agreed upon. This violates the planned strategy and could leave the sponsor without timely information needed for decision-making.

Key Concept

This question covers Determine how to follow and execute planned strategies or frameworks under Determine how to follow and execute planned strategies or frameworks (Project Management Fundamentals and Core Concepts).

Share: