CAPM Practice: Determine how to follow and execute planned strategies or frameworks
Question 64 of 100 in Determine how to follow and execute planned strategies or frameworks
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: 1. Risk management plan identifies monthly risk reviews → Perform monthly risk assessment sessions with the team 2. Communications plan specifies weekly team status meetings → Conduct the status meetings at the scheduled frequency 3. Quality management plan requires peer reviews for all deliverables → Implement peer review process before deliverable approval 4. Stakeholder engagement plan defines quarterly executive briefings → Hold executive briefings each quarter as planned
Explanation
Executing planned strategies means following the documented approach in each management plan. Risk plans require regular risk reviews, communications plans specify meeting frequency and attendees, quality plans define review processes, and stakeholder engagement plans outline interaction timing and methods. Each execution response directly implements its corresponding planned strategy.
**Why not B:** This option incorrectly assigns the risk management plan to quarterly executive briefings (which belongs to stakeholder engagement) and the stakeholder engagement plan to monthly risk assessment sessions (which belongs to risk management). These two execution responses are swapped.
**Why not C:** This option incorrectly assigns the risk management plan to peer reviews (which belongs to quality management), the communications plan to executive briefings (which belongs to stakeholder engagement), the quality plan to risk assessments (which belongs to risk management), and the stakeholder plan to status meetings (which belongs to communications). Every pairing is mismatched.
**Why not D:** This option incorrectly assigns the risk management plan to status meetings (which belongs to communications), the communications plan to peer reviews (which belongs to quality management), the quality plan to executive briefings (which belongs to stakeholder engagement), and the stakeholder plan to risk assessments (which belongs to risk management). All four execution responses are matched to the wrong plans.
Key Concept
This question covers Determine how to follow and execute planned strategies or frameworks under Determine how to follow and execute planned strategies or frameworks (Project Management Fundamentals and Core Concepts).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.