Question 63 of 100 in Determine how to follow and execute planned strategies or frameworks

Pick an answer below — you'll get the explanation instantly, no signup.

Maryam Fuentes is initiating a new product development project at Wavelength Biotech. Senior leadership wants to understand when the organization will realize value from the project investment. During initiation, the benefits realization timeline shows value will be achieved 18 months after project completion. Leadership expected immediate value upon project closure. What should Maryam do FIRST?
Show answer & explanation

Correct answer: Facilitate a discussion with leadership to clarify benefit expectations and the realistic benefits realization timeframe

Explanation

During project initiation, aligning stakeholder expectations with realistic benefit planning is critical. Facilitating a discussion ensures leadership understands when value will be realized and allows for informed decision-making about whether to proceed, adjust scope, or modify expectations.

**Why not B:** Revising the project scope to force immediate benefits may compromise quality or feasibility. Benefits realization timelines are often inherent to the nature of the deliverable, and artificially compressing them could lead to unrealistic commitments or incomplete value delivery.

**Why not C:** While benefits realization may extend beyond project closure, the project manager should not simply ignore the misalignment in expectations. Proceeding without addressing the gap between leadership's expectations and the realistic timeline risks stakeholder dissatisfaction and loss of support.

**Why not D:** Requesting additional budget to accelerate the timeline assumes that money alone can speed up benefits realization, which is often not the case. The first step should be ensuring expectations are aligned before committing additional resources to an approach that may not be feasible.

Key Concept

This question covers Determine how to follow and execute planned strategies or frameworks under Determine how to follow and execute planned strategies or frameworks (Project Management Fundamentals and Core Concepts).