CAPM Practice: Determine how to follow and execute planned strategies or frameworks

Question 19 of 100 in Determine how to follow and execute planned strategies or frameworks

Pick an answer below — you'll get the explanation instantly, no signup.

Safiya Yoon is reviewing the communication management plan for her project at Basalt Digital. What is the PRIMARY purpose of following this planned strategy?
Show answer & explanation

Correct answer: To ensure stakeholders receive the right information at the right time in the right format

Explanation

The primary purpose of a communication management plan is to ensure stakeholders receive appropriate information when they need it and in a format that works for them. This planned strategy guides how, when, and what to communicate throughout the project lifecycle.

**Why not A:** Documenting communications after they occur for historical records is an archival activity, not the primary purpose of a communication management plan. The plan is proactive — it guides future communications to ensure the right information reaches the right stakeholders at the right time.

**Why not C:** Reducing the number of meetings is a potential side benefit of effective communication planning, not its primary purpose. The plan focuses on ensuring stakeholders receive appropriate information effectively, which may or may not involve reducing meeting frequency.

**Why not D:** The communication management plan does not aim to eliminate informal communication. Informal communication is valuable for team collaboration and quick problem-solving. The plan structures formal communications while informal exchanges continue naturally alongside them.

Key Concept

This question covers Determine how to follow and execute planned strategies or frameworks under Determine how to follow and execute planned strategies or frameworks (Project Management Fundamentals and Core Concepts).