CAPM Practice: Determine how to document project controls of predictive, plan-based projects
Question 60 of 85 in Determine how to document project controls of predictive, plan-based projects
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Procurement management and work authorization
Explanation
Authorizing a vendor to begin work involves procurement management (the contractual relationship with the vendor) and work authorization (formally permitting specific work to begin). The work order is a procurement instrument that authorizes the vendor and establishes the formal direction to begin work within the project's governance structure.
**Why not B:** Quality control involves inspecting deliverables against quality standards. Approving a work order to begin vendor work is about authorizing the start of work under a procurement agreement, not inspecting the quality of completed deliverables.
**Why not C:** While vendor management involves stakeholder relationships, approving a work order is specifically a procurement and work authorization action. Stakeholder management encompasses broader engagement activities, not the specific contractual authorization of vendor work.
**Why not D:** Risk management involves identifying, analyzing, and responding to project risks. Issuing a work order to a vendor is a procurement execution action, not a risk management activity, though procurement decisions may be informed by risk analysis.
Key Concept
This question covers Determine how to document project controls of predictive, plan-based projects under Determine how to document project controls of predictive, plan-based projects (Predictive, Plan-Based Methodologies).