CAPMHard
CAPM Practice: Determine how to document project controls of predictive, plan-based projects
A project manager is managing a large infrastructure project. The project has 15 control accounts. The Control Account Manager (CAM) for Control Account 7 reports that his account is on track (CPI = 0.99, SPI = 1.01). However, the project manager notices that 3 activities within CA7 that are not yet started have dependencies on a vendor who just went bankrupt. What should the project manager do?
Key Concept
This question covers Determine how to document project controls of predictive, plan-based projects under Determine how to document project controls of predictive, plan-based projects (Predictive, Plan-Based Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free