Configuration management in a predictive project ensures that:
Show answer & explanation

Correct answer: Product characteristics are formally controlled and changes to specifications are documented and approved

Explanation

Configuration management controls the characteristics of project deliverables — ensuring that any change to approved specifications goes through a formal process. It maintains the integrity of the product baseline, controls versions of documents and deliverables, and ensures stakeholders are always working from current, approved versions.

**Why not A:** Configuration management has nothing to do with computer hardware or software configurations used by team members. It is a project management discipline focused on controlling the characteristics and versions of project deliverables and their specifications.

**Why not B:** Following the "same configuration in agile sprints" conflates IT configuration with project configuration management and introduces agile concepts irrelevant to a predictive project context. Configuration management in predictive projects ensures deliverable specifications are formally controlled.

**Why not D:** Configuring the schedule for resource availability describes resource management or resource leveling, not configuration management. Configuration management controls product specifications and deliverable characteristics, not schedule or resource parameters.

Key Concept

This question covers Determine how to document project controls of predictive, plan-based projects under Determine how to document project controls of predictive, plan-based projects (Predictive, Plan-Based Methodologies).