CAPM Practice: Determine how to document project controls of predictive, plan-based projects
Question 58 of 85 in Determine how to document project controls of predictive, plan-based projects
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Comprehensive plan that integrates all subsidiary plans and baselines for managing the project
Explanation
The project management plan (PMP) is the master planning document that integrates all subsidiary management plans (scope, schedule, cost, quality, risk, communications, procurement, stakeholder, resource) and the three baselines (scope, schedule, cost). It describes how the project will be executed, monitored, controlled, and closed — the comprehensive guide to managing every aspect of the project.
**Why not A:** A single document listing all project deliverables describes the scope statement or WBS dictionary, not the project management plan. The PMP is far more comprehensive, integrating all subsidiary management plans and baselines across every project knowledge area.
**Why not C:** A document created by the sponsor to authorize project work describes the project charter. The project charter is created during initiation by the sponsor, while the project management plan is developed by the project manager and team during planning.
**Why not D:** A high-level summary for stakeholder communication could describe a project brief or executive summary. The project management plan is the detailed, comprehensive guide for managing the project, not a summary-level communication document.
Key Concept
This question covers Determine how to document project controls of predictive, plan-based projects under Determine how to document project controls of predictive, plan-based projects (Predictive, Plan-Based Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free