Skip to content
CAPMEasy

CAPM Practice: Determine how to document project controls for an adaptive project

Question 21 of 60 in Determine how to document project controls for an adaptive project

Pick an answer below — you'll get the explanation instantly, no signup.

In adaptive projects, stakeholder feedback from sprint reviews is used to:
Show answer & explanation

Correct answer: Update the product backlog (add, modify, re-prioritize items) for future sprints

Explanation

Sprint review feedback directly updates the product backlog — not through formal change control, but through the product owner's ongoing backlog management. New items suggested by stakeholders are added; items stakeholders don't value are de-prioritized; existing items may be refined based on feedback. This backlog update is the adaptive mechanism for incorporating stakeholder input.

Key Concept

This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free