CAPM Practice: Determine how to document project controls for an adaptive project
Question 21 of 60 in Determine how to document project controls for an adaptive project
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Update the product backlog (add, modify, re-prioritize items) for future sprints
Explanation
Sprint review feedback directly updates the product backlog — not through formal change control, but through the product owner's ongoing backlog management. New items suggested by stakeholders are added; items stakeholders don't value are de-prioritized; existing items may be refined based on feedback. This backlog update is the adaptive mechanism for incorporating stakeholder input.
Key Concept
This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).