CAPM Practice: Determine how to document project controls for an adaptive project
Question 22 of 60 in Determine how to document project controls for an adaptive project
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Product analytics and usage metrics showing whether delivered features are being adopted and used
Explanation
Product analytics track actual usage of delivered features — do users use the login workflow? How many customers completed the checkout? These outcome metrics reveal whether delivered work creates real value. A team can achieve perfect velocity and sprint completion while building features nobody uses. Product analytics connect agile delivery activity to business impact.
**Why not A:** The number of stories accepted by the product owner shows that work met its acceptance criteria and was completed. It does not show whether customers actually use the delivered features after release, so it measures output, not adoption.
**Why not C:** A sprint burndown chart tracks the remaining work within a sprint and shows how completed story points progress. It shows what the team finished, which is exactly what the team already tracks. It says nothing about whether customers are using that work.
**Why not D:** A velocity trend chart shows how much work the team completes per sprint over time. It is useful for forecasting and capacity planning, but it measures delivery throughput, not whether delivered features are being adopted by customers.
Key Concept
This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).