CAPM Practice: Determine how to document project controls for an adaptive project
Question 28 of 60 in Determine how to document project controls for an adaptive project
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: A shared standard that defines when a work item is complete, ensuring consistent quality across the team
Explanation
The Definition of Done is an agreed-upon quality checklist that work must meet before being considered complete. It's a key quality control tool that creates shared understanding and prevents 'done but not really done' issues.
**Why not A:** The Definition of Done is not an authorization or permissions list; it is a quality standard applied to the work itself, not to who may approve it. Access control and sign-off authority are separate governance concerns entirely distinct from quality criteria.
**Why not B:** Client sign-off at project close is a formal acceptance activity, not the Definition of Done. The DoD is an internal team standard applied continuously throughout development, not a single end-of-project contract document.
**Why not C:** Acceptance criteria belong to individual user stories and define what a specific story must accomplish; the DoD is a broader team-wide quality checklist applied to every work item. It is an informal working agreement — not a legal contract — and it applies to all increments rather than to a single final deliverable.
Key Concept
This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).