CAPM Practice: Determine how to document project controls for an adaptive project
Question 29 of 60 in Determine how to document project controls for an adaptive project
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Changes are embraced through backlog refinement and reprioritization rather than formal change requests
Explanation
Adaptive projects embrace change through continuous backlog refinement. New requirements or changes are added to the backlog and prioritized accordingly, rather than going through formal change request and approval processes.
Key Concept
This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).