Skip to content
CAPMEasy

CAPM Practice: Determine how to document project controls for an adaptive project

Question 14 of 60 in Determine how to document project controls for an adaptive project

In adaptive project management, retrospective action items should be:
Show answer & explanation

Correct answer: Assigned owners, added to the sprint backlog as tasks, and tracked to completion

Explanation

Retrospective improvements must be actionable and tracked. Best practice assigns each action item an owner, adds it to the sprint backlog (so it gets planned, worked, and reviewed like any other work), and verifies completion. Improvements that aren't tracked are rarely implemented. Treating retrospective actions with the same rigor as product work signals the team's commitment to continuous improvement.

Key Concept

This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free