CAPM Practice: Determine how to document project controls for an adaptive project

Question 15 of 60 in Determine how to document project controls for an adaptive project

Pick an answer below — you'll get the explanation instantly, no signup.

An adaptive team is asked to produce a formal change request when the product owner re-prioritizes the backlog between sprints. This requirement:
Show answer & explanation

Correct answer: Is unnecessary and adds overhead; backlog re-prioritization by the product owner is a normal adaptive activity that doesn't require formal change requests

Explanation

Backlog re-prioritization between sprints is exactly what the product owner is supposed to do — it's one of the primary value-generating activities in adaptive approaches. Requiring a formal change request for normal backlog management adds bureaucratic overhead that conflicts with the adaptive principle of responding to change. Change requests in adaptive contexts apply to fundamental project parameters (budget, major scope changes) not to routine backlog management.

Key Concept

This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).