Skip to content
CAPMMedium

CAPM Practice: Determine how to document project controls for an adaptive project

Question 15 of 60 in Determine how to document project controls for an adaptive project

Pick an answer below — you'll get the explanation instantly, no signup.

An adaptive team is asked to produce a formal change request when the product owner re-prioritizes the backlog between sprints. This requirement:
Show answer & explanation

Correct answer: Is unnecessary and adds overhead; backlog re-prioritization by the product owner is a normal adaptive activity that doesn't require formal change requests

Explanation

Backlog re-prioritization between sprints is exactly what the product owner is supposed to do — it's one of the primary value-generating activities in adaptive approaches. Requiring a formal change request for normal backlog management adds bureaucratic overhead that conflicts with the adaptive principle of responding to change. Change requests in adaptive contexts apply to fundamental project parameters (budget, major scope changes) not to routine backlog management.

**Why not A:** Adaptive projects do not require formal documentation for every change. The backlog is expected to evolve as the team learns, and the product owner owns its ordering. Treating each re-prioritization as a formal change applies predictive change control where it does not fit and slows the team's ability to respond to new information.

**Why not C:** Escalating to senior management is premature. The better first step is to explain directly to those requesting the change requests how backlog management works in adaptive approaches and agree on lightweight transparency, such as a visible backlog and sprint reviews. Escalation should be reserved for cases where direct conversation fails.

**Why not D:** The Agile Manifesto contains no requirement for formal change requests. It values responding to change over following a plan and individuals and interactions over processes and tools. Transparency in adaptive approaches comes from a visible backlog and regular reviews, not formal change paperwork.

Key Concept

This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free