CAPM Practice: Determine how to document project controls for an adaptive project

Question 8 of 60 in Determine how to document project controls for an adaptive project

Pick an answer below — you'll get the explanation instantly, no signup.

An adaptive team decides to use a cumulative flow diagram (CFD) in addition to burndown charts. What additional insight does a CFD provide?
Show answer & explanation

Correct answer: Visualization of workflow and identification of bottlenecks by showing work items in each state over time

Explanation

A Cumulative Flow Diagram shows the number of items in each workflow state (To Do, In Progress, Done) over time. It reveals: throughput trends, bottlenecks (when one stage accumulates items while others don't), cycle time patterns, and flow stability. A widening 'In Progress' band indicates work piling up without being completed — a bottleneck requiring attention.

**Why not A:** A CFD is not a velocity tool. Velocity is the amount of work (e.g., story points) completed per iteration, which burndown/burnup charts and iteration records already capture. The CFD's added value is visibility into flow through workflow states, not a better velocity figure.

**Why not C:** A CFD shows aggregate counts of items in each state over time, not the completion date of individual stories. Item-level dates come from the board or tracking tool, not from the diagram.

**Why not D:** A CFD shows team-level flow of work items and does not break out individual contributions. Agile measurement focuses on the team's delivery rather than tracking individual output.

Key Concept

This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).