CAPM Practice: Determine how to document project controls for an adaptive project
Question 8 of 60 in Determine how to document project controls for an adaptive project
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Visualization of workflow and identification of bottlenecks by showing work items in each state over time
Explanation
A Cumulative Flow Diagram shows the number of items in each workflow state (To Do, In Progress, Done) over time. It reveals: throughput trends, bottlenecks (when one stage accumulates items while others don't), cycle time patterns, and flow stability. A widening 'In Progress' band indicates work piling up without being completed — a bottleneck requiring attention.
Key Concept
This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).