Skip to content
CAPMEasy

CAPM Practice: Determine how to document project controls for an adaptive project

Question 9 of 60 in Determine how to document project controls for an adaptive project

A Scrum team's sprint review demonstrates completed work to stakeholders. The team discovers that a story they completed doesn't match what the product owner expected. What should have prevented this?
Show answer & explanation

Correct answer: Clear acceptance criteria defined for the story before the sprint began, against which completion is verified

Explanation

Stories without clear acceptance criteria set teams up for 'completion misalignment' — where the team believes they are done but the work doesn't meet the product owner's expectation. Well-defined acceptance criteria, agreed before the sprint begins, provide testable conditions that both the team and PO share. The sprint review should not be the first time the PO sees what was built.

Key Concept

This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free