CAPM Practice: Determine how to document project controls for an adaptive project
Question 9 of 60 in Determine how to document project controls for an adaptive project
Show answer & explanation
Correct answer: Clear acceptance criteria defined for the story before the sprint began, against which completion is verified
Explanation
Stories without clear acceptance criteria set teams up for 'completion misalignment' — where the team believes they are done but the work doesn't meet the product owner's expectation. Well-defined acceptance criteria, agreed before the sprint begins, provide testable conditions that both the team and PO share. The sprint review should not be the first time the PO sees what was built.
Key Concept
This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free