CAPM Practice: Determine how to document project controls for an adaptive project

Question 9 of 60 in Determine how to document project controls for an adaptive project

Pick an answer below — you'll get the explanation instantly, no signup.

A Scrum team's sprint review demonstrates completed work to stakeholders. The team discovers that a story they completed doesn't match what the product owner expected. What should have prevented this?
Show answer & explanation

Correct answer: Clear acceptance criteria defined for the story before the sprint began, against which completion is verified

Explanation

Stories without clear acceptance criteria set teams up for 'completion misalignment' — where the team believes they are done but the work doesn't meet the product owner's expectation. Well-defined acceptance criteria, agreed before the sprint begins, provide testable conditions that both the team and PO share. The sprint review should not be the first time the PO sees what was built.

**Why not A:** Daily progress reports tell the product owner how far along a story is, not whether the team and PO share the same understanding of what 'done' looks like. The team could report steady progress toward the wrong outcome. Status reporting does not replace agreed, testable conditions of acceptance.

**Why not B:** More detailed technical documentation describes how the solution is built, not what the product owner expects it to do. The misalignment is about expected outcomes, not technical detail, and agile approaches favor working software and shared understanding over comprehensive documentation.

**Why not D:** A formal change request is a change-control mechanism for modifying agreed scope; it does not create a shared definition of what the story must deliver. Nothing in the scenario indicates the story was changing — the problem is that expectations were never made explicit and verifiable before the work began.

Key Concept

This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).