CAPM Practice: Determine how to document project controls for an adaptive project
Question 42 of 60 in Determine how to document project controls for an adaptive project
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Both completed work and total scope, making scope changes visible
Explanation
A burnup chart plots both completed work and total scope on the same chart. When scope increases, the total line rises, making scope growth transparent — something a burndown chart doesn't easily show.
**Why not B:** Remaining defects are not what a burnup chart tracks. Defects are typically monitored with separate quality metrics such as defect trend charts; neither burnup nor burndown charts are primarily defect reports.
**Why not C:** Burnup charts show team-level progress toward total scope, not individual contributions. Agile metrics focus on the team's collective output rather than measuring individual team members.
**Why not D:** Comparing the cost of completed work to planned cost is earned value analysis (earned value versus planned value), not something a burnup chart displays.
Key Concept
This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).