Skip to content
CAPMEasy

CAPM Practice: Determine how to document project controls for an adaptive project

Question 42 of 60 in Determine how to document project controls for an adaptive project

What does a burnup chart show that a burndown chart does not?
Show answer & explanation

Correct answer: Both completed work and total scope, making scope changes visible

Explanation

A burnup chart plots both completed work and total scope on the same chart. When scope increases, the total line rises, making scope growth transparent — something a burndown chart doesn't easily show.

Key Concept

This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free