CAPM Practice: Determine how to document project controls for an adaptive project
Question 43 of 60 in Determine how to document project controls for an adaptive project
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: The time from when a request is received until it is delivered, measuring end-to-end responsiveness
Explanation
Lead time measures the total time from a customer request entering the system until it is delivered. It's a key Kanban metric that reveals overall process efficiency from a customer perspective.
Key Concept
This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free