CAPM Practice: Determine how to document project controls for an adaptive project
Question 43 of 60 in Determine how to document project controls for an adaptive project
In adaptive project controls, what does 'lead time' measure?
Show answer & explanation
Correct answer: The time from when a request is received until it is delivered, measuring end-to-end responsiveness
Explanation
Lead time measures the total time from a customer request entering the system until it is delivered. It's a key Kanban metric that reveals overall process efficiency from a customer perspective.
Key Concept
This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).