Skip to content
CAPMMedium

CAPM Practice: Determine how to document project controls for an adaptive project

Question 43 of 60 in Determine how to document project controls for an adaptive project

Pick an answer below — you'll get the explanation instantly, no signup.

In adaptive project controls, what does 'lead time' measure?
Show answer & explanation

Correct answer: The time from when a request is received until it is delivered, measuring end-to-end responsiveness

Explanation

Lead time measures the total time from a customer request entering the system until it is delivered. It's a key Kanban metric that reveals overall process efficiency from a customer perspective.

Key Concept

This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).

Share:

All 1,500+ CAPM questions are free

Sign up to track your progress, see detailed analytics, and get personalized study recommendations.

Sign Up Free