CAPM Practice: Determine how to document project controls for an adaptive project
Question 50 of 60 in Determine how to document project controls for an adaptive project
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: In the backlog items themselves with dependency tags, and resolved through cross-team communication events
Explanation
In adaptive projects, dependencies are flagged directly on backlog items and resolved through regular cross-team synchronization (Scrum of Scrums, PI Planning, or informal communication), keeping dependency management lightweight.
**Why not B:** Agile teams still have dependencies; ignoring them leads to blocked work and delays.
**Why not C:** PMO-approved formal tooling adds heavyweight overhead that adaptive approaches avoid.
**Why not D:** Relying only on quarterly meetings is too infrequent to resolve dependencies that arise every iteration.
Key Concept
This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).