CAPM Practice: Determine how to document project controls for an adaptive project
Question 51 of 60 in Determine how to document project controls for an adaptive project
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Calculating cost per story point and comparing feature delivery value estimates against actual delivery costs per iteration
Explanation
Adaptive projects can track ROI by measuring cost per story point (team cost / velocity) and comparing it against business value estimates for features delivered. This enables value stream thinking and better prioritization.
**Why not A:** Changing scope does not prevent ROI tracking. Adaptive projects measure value incrementally each iteration, comparing the cost of delivered work against the business value it generates.
**Why not C:** A one-time NPV calculation made at inception and never updated ignores what is learned each iteration. Adaptive control relies on regularly reassessing value as priorities and estimates change.
**Why not D:** Earned value management measures cost and schedule performance against a baseline, not the business value of delivered features. Applying it to story points tracks progress but does not show the return each feature delivers.
Key Concept
This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).
All 1,500+ CAPM questions are free
Sign up to track your progress, see detailed analytics, and get personalized study recommendations.
Sign Up Free