CAPM Practice: Determine how to document project controls for an adaptive project
Question 51 of 60 in Determine how to document project controls for an adaptive project
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: Calculating cost per story point and comparing feature delivery value estimates against actual delivery costs per iteration
Explanation
Adaptive projects can track ROI by measuring cost per story point (team cost / velocity) and comparing it against business value estimates for features delivered. This enables value stream thinking and better prioritization.
Key Concept
This question covers Determine how to document project controls for an adaptive project under Determine how to document project controls for an adaptive project (Agile Frameworks/Methodologies).