CAPM Practice: Determine how to conduct stakeholder communication
Question 61 of 67 in Determine how to conduct stakeholder communication
Pick an answer below — you'll get the explanation instantly, no signup.
Show answer & explanation
Correct answer: A systematic review of whether the project's communication plan is achieving its goals — assessing whether stakeholders are informed, whether communications are effective, and identifying gaps or inefficiencies
Explanation
When stakeholder feedback reveals information gaps, misalignments, or communication fatigue, a communication audit examines current practices against intended objectives. BAs may recommend audits when repeated misunderstandings suggest systematic communication failures, then use findings to redesign the communication approach.
**Why not A:** A communication audit is not limited to project close. It can and should be conducted at various points throughout a project to assess whether communication strategies are effective and to make adjustments as needed. Waiting until close would miss opportunities to improve stakeholder engagement during execution.
**Why not B:** A communication audit is not a financial audit of communication expenses. While cost tracking is a valid project management activity, a communication audit evaluates the effectiveness, frequency, and quality of communication channels and messages rather than their monetary cost.
**Why not D:** A communication audit is not a legal review for compliance purposes. Legal reviews focus on regulatory and contractual obligations, whereas a communication audit assesses whether stakeholders are receiving the right information through the right channels at the right time to support project success.
Key Concept
This question covers Determine how to conduct stakeholder communication under Determine how to conduct stakeholder communication (Business Analysis Frameworks).